Manufacturing / Production Line Setup

EV Charger Production Line and Factory Setup

A production line is a capacity, quality and safety decision at once, and those three pull against each other as volume rises.

The common failure is designing for pilot volume and finding that the constraints change at rate. Takt becomes binding, manual steps that were acceptable become bottlenecks, and test coverage that passed a careful first batch stops catching drift. Specification therefore starts with volume and variant mix, not with equipment.

Request a production-line plan

For Investors, OEMs, manufacturers, consultancies

Inputs we need before designing anything

  • Product variants, including power levels, connector types and enclosure options
  • Annual volume for the first three years, by variant
  • Shift model and available working days
  • Target local content level, which determines how much is assembled versus received
  • PCBA build or buy decision
  • Target cycle time, or the constraint that sets it
  • Available floor area, power supply and environmental conditions

Volume forecasts are always uncertain. What matters is the ratio between the low and high case, because that determines whether the line should be manual and flexible or fixtured and fast.

Process flow

  1. 1

    Incoming quality control

    Verify parts against specification and reject before they enter stock. Critical components need certificate checks, not just count checks.

  2. 2

    Subassembly

    Harness preparation, module preassembly, anything that can be built off the main line to protect takt.

  3. 3

    Final assembly

    Mechanical build, harness routing, torque controlled fastening, sealing.

  4. 4

    Firmware programming

    Firmware, configuration and identity applied at a controlled station.

  5. 5

    End-of-line test

    Full functional and safety relevant sequence with recorded results.

  6. 6

    Final inspection

    Workmanship and cosmetic verification against defined criteria.

  7. 7

    Burn-in where specified

    Applied when the product or customer requires it, sized against takt.

  8. 8

    Packing and despatch

    Per packing specification, with traceability retained.

Line layout

Layout decides material flow, and material flow decides whether the line can be audited. The design separates ESD zones, isolates high voltage test from general assembly, and gives work in progress, rework and quarantine physically distinct locations.

  • Single direction material flow, with no crossing of good and rejected stock
  • ESD protected area covering all board handling stations
  • High voltage test physically separated with interlocked access
  • Defined work in progress buffers sized to the bottleneck
  • Rework station with its own tooling and its own records
  • Quarantine that cannot be casually re-entered into stock

Station tooling

Swipe to compare

StationTypical tooling
Incoming inspectionMeasurement equipment, sampling plan, reference samples
SubassemblyCrimp tools with calibration, cutting and stripping equipment, fixtures
Mechanical assemblyCalibrated torque drivers, assembly fixtures, part presentation
ProgrammingProgramming fixture, host system, controlled credential source
EOL testTest fixture, instrumentation, safety interlocks, golden units
InspectionWorkmanship reference samples, controlled lighting, magnification where needed
LabellingPrinter, scanner, verification of applied identity
PackingPacking fixtures, weight verification where used

Every measuring or torque applying tool needs a calibration interval and an owner. A torque driver with no calibration record makes the entire build record unverifiable.

Capacity model

The capacity model connects volume to staffing and equipment. It covers cycle time per station, takt derived from demand and available time, staffing per shift, parallel stations where a step exceeds takt, the identified bottleneck, an overall equipment effectiveness assumption and the buffer sizing that protects rate.

State the OEE assumption explicitly. A line planned at theoretical throughput will miss its number, and the gap gets blamed on operators rather than on the plan.

Quality gates

  • Incoming: sampling against defined criteria, with reaction plan for failures
  • In process: torque verification, crimp pull testing, visual checkpoints
  • End of line: full sequence, pass required to proceed
  • Audit sampling: periodic deeper test on units that already passed
  • Traceability: every unit linked to its parts, process records and test results

Pilot and ramp

  1. 1

    Engineering build

    Small quantity built by engineering to validate the process and the documentation.

  2. 2

    Controlled pilot

    Built by production operators, with engineering present, at low rate.

  3. 3

    Rate trial

    Demonstrate the line can hold takt and yield over a sustained run.

  4. 4

    Start of production

    Released against defined criteria, not against a calendar date.

  5. 5

    Stabilization

    Monitored window where yield, defect Pareto and early field data are reviewed jointly.

Training matrix and factory readiness

Every station has a defined competence requirement, and every operator has a record of which stations they are signed off on. Unsigned operators do not run stations. This is the control that makes yield data meaningful.

Before the first production shipment, a factory readiness audit checks documentation control, calibration status, training records, ESD compliance, traceability, and the physical separation of good, rework and quarantined stock.

Want this applied to your own site?

Request a production-line plan

Technically reviewed by Deepu Joy, Director of Products and Delivery. Last reviewed 2026-08-29.

Frequently asked questions

What determines how many stations we need?

Takt time derived from your volume and shift model, compared against the cycle time of each process step. Any step exceeding takt needs parallel stations or a redesign.

Do we need burn-in?

Only where the product specification or your customer requires it. Burn-in consumes floor space and takt, so it is specified deliberately rather than by default.

How much floor area does an AC charger line need?

It depends on variant mix, volume and how much subassembly is done locally. The layout is derived from the process flow and capacity model rather than from a standard figure.

Can we start manual and automate later?

Yes, and for most first lines that is the right choice. Manual lines absorb variant changes and forecast error far better than fixtured ones.

Who owns calibration?

A named person at your factory. Every torque, measurement and test device needs an interval, a record and an owner, or the build record cannot be defended.

What is a factory readiness audit?

A structured check before first production shipment covering documentation control, calibration, training records, ESD, traceability and material segregation.

Request a production-line plan

Send the seven inputs above and we will return a process flow, layout concept, station list and capacity model sized to your volume.

Request a production-line plan