Guides / Approvals

EV Charging Guidelines and Approvals in India

The approval path for a charging installation is not one process. It is several, and which apply depends on answers you can establish in an afternoon.

Requirements differ by state, by connection category, by whether the installation is public or captive, and by whether you sell electricity or provide charging as a service. Establishing which case you are in comes before asking what the requirements are.

Talk through your case

For Site owner, developer, consultant

01

The questions that decide the route

Swipe to compare

QuestionWhy it changes the answer
Public or captive?Access by the public generally brings additional obligations
Selling electricity, or a service?Changes the regulatory character of the transaction
Existing connection or new?A new or upgraded connection is a separate process with its own timeline
Connection categoryDomestic, commercial and industrial categories carry different rules and tariffs
Which state?Several requirements are set at state level rather than centrally
Landlord or owner?Consent and wayleave may be required before anything electrical starts

Answering these six determines who you need to speak to. Asking a general question about approvals before answering them produces a general answer that fits nobody.

02

Who holds the answer

  • Your electricity distribution licensee, for connection, category, tariff and metering
  • The state electricity regulatory commission, for tariff and any charging-specific orders
  • Local authority or municipal body, for civil work, access and signage
  • The property owner, for consent, wayleave and structural permission
  • A licensed electrical contractor and, where applicable, the electrical inspectorate

Requirements change, and they differ between states. Confirm the current position with these bodies rather than relying on any published summary, this page included.

03

Why no list of requirements appears here

Because a list would be wrong somewhere and stale eventually, and a reader acting on a stale requirement is worse off than one who was told to check. Policy in this area has moved repeatedly, and pages that confidently list rules are frequently the ones that have not been revisited.

What is durable is the structure: which questions determine your route, and which body holds each answer.

04

Start the approvals in parallel

Approval and any supply work usually set the schedule, not procurement or installation. Beginning them once the hardware arrives is the most common way a technically ready site sits unusable.

05

Safety obligations do not depend on the route

Whatever approval path applies, the installation must be electrically safe, correctly protected and properly earthed, and carried out by someone competent to do so. That obligation is independent of whether the site is public, captive, sold or free.

06

The constraint that decides most private installations

Approvals get the attention, and they matter. What actually decides whether a private installation works is usually the supply position and the hour the demand arrives.

In apartments, which is where most private multi-vehicle charging happens, utilisation is the highest of any AC site we operate and it concentrates overnight. That is the same window the building is least able to absorb. An association that sizes for simultaneous charging will be told it needs a supply upgrade. One that schedules the load frequently does not.

The second constraint is connectivity. Basement and podium parking is where mobile signal fails, and any design that requires a backend to authorise a session will fail there intermittently. That is a specification decision, made before installation, not something to discover afterwards.

Want this applied to your own site?

Talk through your case

Technically reviewed by Deepu Joy, Director of Products and Delivery. Last reviewed 2026-08-29.

Frequently asked questions

Do I need approval to install an EV charger?

It depends on whether the installation is public or captive, whether you sell electricity, and your connection category and state. Those answers determine the route, which is why establishing them comes first.

Who do I ask?

Your electricity distribution licensee for connection and tariff, the state regulatory commission for charging-specific orders, the local authority for civil and access matters, and the property owner for consent.

Why are the requirements not listed here?

Because they differ by state and change over time. A reader acting on a stale requirement is worse off than one who was told which body to confirm with.

Does selling electricity change things?

It generally changes the regulatory character of the transaction, which is why it is one of the six questions that determine your route.

When should approvals start?

At the beginning. Approvals and supply work usually set the schedule, and starting them when hardware arrives is how a finished site sits unusable.

Talk through your case

Tell us the site, whether it is public or captive and your connection position, and we will tell you which route applies.

Talk through your case